Click to Home

Go To Site Search
Holloway/Stanich Highlands Improvements
City Project 09-13

The proposed project area is illustrated on the attached project location map and consists of the Stanich Highlands area (Ripley Avenue, Kingston Avenue, Price Avenue, Hazel Street, Stanich Place, and Ruth Street) north of Larpenteur Avenue and southeast of North St. Paul Road; and of Holloway Avenue from North St. Paul Road to McKnight Road.  Staff has been coordinating with North Saint Paul staff since Holloway Avenue is a border street.  Street and utility improvements for these street segments have been listed in the City’s Capital Improvement Plan (CIP) for 2009-2013. 

 

Approximately 1.7 miles of street are proposed to be reconstructed or resurfaced as a part of this project.  Holloway Avenue between Beebe Street and Furness Street is in better condition than other streets in the project area and is proposed to be improved by bituminous mill and overlay.  All other street segments are proposed to be fully reconstructed.  Concrete curb and gutter is proposed along all streets.  On streets with existing concrete curb and gutter, curb and gutter spot repair is proposed in areas not requiring full curb construction.  It is proposed that existing street widths will be maintained, except in areas where the street width exceeds 32 feet, in which case a 32-foot width is proposed.

 

There is existing storm sewer along segments of the project area.  New storm structures and storm sewer pipe will be needed to accommodate the new curb and gutter construction and potential changes in roadway width.  Repairs will be made to existing structures and pipe as needed.  Repairs to the sanitary sewer system are proposed as identified through televising of the mainline and services.

 

Due to a significant number of water main breaks in the Stanich Highlands area, water main in this area is proposed to be fully replaced at the cost of SPRWS.

 

The residents in the Stanich Highlands and Holloway Avenue neighborhoods have been contacted via mailings and have been informed about the City’s proposed street reconstruction.  Residents with questions regarding the mailing were encouraged to call the Public Works Department.  A neighborhood meeting was held on the evening of June 16, 2009 at the Maplewood Community Center.  A brief presentation was given. 


Week of July 5th Construction Activity -- Stanich Highlands Area

The contractor will begin raising manhole covers in the roadways in preparation for the final lift of paving this week.

Sod work is in progress on Kingston Avenue.  Boulevard and sod work is scheduled through to next Wednesday, July 14th.

Preparations for the final lift of paving will occur on Thursday, July 15th with the final lift of paving going down on Friday, July 16th.


Week of July 5th Construction Activity -- Holloway Avenue
Boulevard restoration has completed on Holloway Avenue as well as any miscellaneous driveway replacements and patching.

The contractor will work to raise manhole covers on the roadway this week in preparation for the final lift of paving.

Milling of the section of roadway between Beebe Road and Furness Street will occur Thursday, July 15th. 

The final lift of paving on Holloway will occur on Friday, July 16th.

Construction for the rest of June
Base paving of Stanich, Price and Ruth has been tenatively scheduled for June 27th. 

The final lift of paving will occur the 2nd week in July.

Private Driveways
For residents that are interested in replacing their existing driveways as part of the road construction work, the City is offering a private driveway replacement program.  We offer standard asphalt or concrete (non-reinforced) paved driveway types.  Please contact Steve Kummer if you are interested in having the City complete an estimate for a private driveway.

General Construction Information
  • Please obey the traffic control signage in the area.  It is available for your safety.  Utilize posted detours.  This will reduce wear and tear on your vehicle driving over a gravel surface.
  • Drive slow!  This will keep the amount of dust down and will make the roadway surface last longer while it is without pavement.
  • Be patient.  We likely won't be back anytime soon to fully reconstruct the roadway to this extent.  Wait out the 6 weeks it takes to do the work and be patient and cooperative with the construction crews.  We promise that your road will be put back together regardless of some of the hurtles that go along with a street reconstruction project.

Project Contacts

Prime Contractor
Tower Asphalt, Inc.
Stewart Packer  (651) 789-1176
Mike Leuer        (651) 436-8444            

Project Representative (Field Contact)
Brian Gohl - Kimley Horn and Associates
(651) 769-7252

Preject Representative (City of Maplewood Contact)

Steve Kummer

Staff Engineer / Project Rep.

Phone: (651) 249-2418

Email: 



1830 County Road B East • Maplewood, MN 55109 • Ph: (651) 249-2000