Residents or contractors planning to dig or otherwise disturb or excavate soil are required to call Gopher State One Call at (651) 454-0002 at least two business days before actually digging.

GSOC will notify utility providers to locate services that are installed in the area.

The attendant at GSOC will ask for detailed information about the work site. Some of the questions include:
  • What type of work is being done
  • Where is the work site located
  • How long will the work take
  • What are the township, range, section and quarter section coordinates, the legal description, of the work site

The legal description of the property is very important and may be obtained from your property tax statement.

Once the call is complete, a ticket number will be issued. This ticket number is very important and should be kept until the work is completed in case any questions arise.

It also serves as proof that the call center was notified. It is helpful to mark the proposed excavation site with white wooden stakes or white paint.

Once notified, the utility companies determine whether they need to locate their underground utilities near the proposed dig site.

They may not mark any private utilities, i.e. power to garage, gas grill or LP lines, etc. If they determine that they do not need to locate their utilities, they call back to GSOC and indicate this.

After 24 hours from the initial call, a person may call back to GSOC, provide the attendant with the ticket number, and they will be able to verify what utilities have cleared the area.

If the utilities cannot clear the work area, they will mark the location of underground utilities on the lot. If the dig site has been marked with white stakes, the utilities will mark out that area.

If no white stakes are used, they may mark the entire lot. Utilities usually use paint or flags to mark the area, depending on soil and weather conditions.

Color Code for Marking Underground Utility Lines
  • Red - Electric
  • Yellow - Gas-Oil-Steam
  • Orange - Communication CATV
  • Blue - Water
  • Purple - Reclaimed water, irrigation
  • Green - Sewer
  • Pink - Temporary survey markings
  • White - Proposed excavation

After the underground utilities have been marked, and the 48-hour time frame has elapsed, the excavation work may commence.

A minimum clearance of two feet between a marked and unexposed underground utility and the cutting edge or point of any power-operated equipment must be kept.

If the excavation is required within two feet of any marking, the excavation should be performed very carefully with hand tools.

If there has been any damage to an underground utility, or if there is a suspicion of damage, it is the excavator’s responsibility to notify the utility company directly.

If the situation appears to be dangerous, call 911.