Londin-Highpoint Area Pavement Rehabilitation

The City is happy to announce that improvements in the Londin-Highpoint area are underway! If you live in the project area, the phrase that likely comes to mind is - 'It's about time'. We get it. The streets in this neighborhood had some of the lowest ratings of all City streets.

This project includes the full-depth reclamation (grinding) of the project streets, the replacement of severely deteriorate concrete curb and gutter, and the installation of 2 new layers of bituminous pavement.

  1. Jon Jarosch

    Assistant City Engineer
    Phone: (651) 249-2405

Proposed Timeline

Target Dates Actions
September 12, 2017 Project Information Packet Mailed
November 14, 2017 Neighborhood Meeting from 6:00PM - 7:30PM in Room B at the Maplewood Community Center
February 12, 2018 Council accepts Feasibility Report, Calls for Public Hearing and Authorizes Preparation of Plan and Specs
March 12, 2018 Council held Public Hearing and Ordered Improvement
April 9, 2018 Council Approved Plans, Authorized Ad for Bid, and Authorized Preparation of Assessment Role
April 23, 2018 Council Accepted Assessment Roll and Ordered Assessment Hearing
May 4, 2018 Bid Opening
TBA Construction Begins in Project Area
Location Map 17-19

Streets Impacted:

Crestview Drive, Highpoint Curve, King Avenue, Londin Lane, Marnie Street, Pond Avenue